Salinas Road Interchange

Description: Highway 1 from south of Jensen Rd to Trafton Road near Watsonville. Construct new interchange and convert 2-lane highway to 2-lane expressway with access control and frontage roads.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Monterey
City
Zip Code 95039, 95076
 
Senate District
15
Assembly District 27
Congressional District 17
 
Caltrans District
05
 
 
County/State Route Monterey 1
Postmile Begin/End 99.9 R  101.5
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  673    729  
Peak Period Time Savings (minutes)  45561    49354  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Richard Rosales (805) 549-3792   richard.rosales@dot.ca.gov
Design (PS&E) Phase
Caltrans Richard Rosales (805) 549-3792   richard.rosales@dot.ca.gov
Right of Way Phase
Caltrans Nicholas Heisdorf (805) 835-6558   nicholas.heisdorf@dot.ca.gov
Construction Phase
Caltrans Brandy Rider (805) 549-3620   brandy.rider@dot.ca.gov
 
Corridor System Management Plan
Caltrans Claudia Espino (805) 549-3640   claudia.espino@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $938 $938
CMIA
$37,061 $-18,493 $18,568
Non-bond Funding
State/Federal*
$11,455 $730 $12,185
Non Budgeted ETC
$0 $0 $0
 
Total**** $48,516 $-16,825 $31,691

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$3,068 $0 $3,068 $2,899
Design(PS&E)
$2,950 $0 $2,950 $3,853
Right of Way
$5,437 $0 $5,437 $6,651
Construction
$37,061 $-16,825 $20,236 $20,306
 
Total* $48,516 $-16,825 $31,691 $33,708

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2000 

06/01/2006 
07/01/2000 

06/01/2006 
07/01/2000 

06/01/2006 
100  08/01/2001 

06/26/2006 
-13 

-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2006 

01/01/2009 
06/01/2006 

01/01/2009 
06/01/2006 

01/01/2009 
100  06/26/2006 

12/31/2008 
-1 

Begin Right of Way Phase

End Right of Way Phase
11/01/2006 

11/01/2008 
11/01/2006 

11/01/2008 
11/01/2006 

11/01/2008 
100  09/05/2006 

11/13/2008 


Begin Construction Phase

End Construction Phase
05/01/2009 

07/01/2011 
05/01/2009 

07/01/2011 
05/01/2009 

07/01/2011 
100  10/07/2009 

03/20/2014 
-5 

-33 
Begin Closeout Phase

End Closeout Phase
07/01/2011 

12/01/2012 
07/01/2011 

12/01/2012 
07/01/2011 

12/01/2012 
50  03/20/2014 

12/29/2023 
-33 

-135 
Corridor System Management Plan
Adoption Date 09/01/2010    09/01/2010   
Implementation Date 10/01/2010    10/01/2010   
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 673 729
Peak Period Time Savings (minutes) 45561 49354

Bond Funding Cost
Adopted:
$37,061,000
Current Approved:
$18,568,000
Actual Expenditures:
$18,568,000

 

Status as of December 31, 2023.