Salinas Road Interchange |
Description: Highway 1 from south of Jensen Rd to Trafton Road near Watsonville. Construct new interchange and convert 2-lane highway to 2-lane expressway with access control and frontage roads.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Monterey |
City | |
Zip Code | 95039, 95076 |
Senate District |
15 |
Assembly District | 27 |
Congressional District | 17 |
Caltrans District |
05 |
County/State Route | Monterey 1 |
Postmile Begin/End | 99.9 R 101.5 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 673 | 729 |
Peak Period Time Savings (minutes) | 45561 | 49354 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Richard Rosales | (805) 549-3792 | richard.rosales@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Richard Rosales | (805) 549-3792 | richard.rosales@dot.ca.gov | |
Right of Way Phase |
Caltrans | Nicholas Heisdorf | (805) 835-6558 | nicholas.heisdorf@dot.ca.gov | |
Construction Phase |
Caltrans | Brandy Rider | (805) 549-3620 | brandy.rider@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Claudia Espino | (805) 549-3640 | claudia.espino@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $938 | $938 | ||||
CMIA |
$37,061 | $-18,493 | $18,568 | ||||
Non-bond Funding | |||||||
State/Federal* |
$11,455 | $730 | $12,185 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $48,516 | $-16,825 | $31,691 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$3,068 | $0 | $3,068 | $2,899 | |||
Design(PS&E) |
$2,950 | $0 | $2,950 | $3,853 | |||
Right of Way |
$5,437 | $0 | $5,437 | $6,651 | |||
Construction |
$37,061 | $-16,825 | $20,236 | $20,306 | |||
Total* | $48,516 | $-16,825 | $31,691 | $33,708 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
07/01/2000 06/01/2006 |
07/01/2000 06/01/2006 |
07/01/2000 06/01/2006 |
100 | 08/01/2001 06/26/2006 |
-13 -1 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/01/2006 01/01/2009 |
06/01/2006 01/01/2009 |
06/01/2006 01/01/2009 |
100 | 06/26/2006 12/31/2008 |
-1 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
11/01/2006 11/01/2008 |
11/01/2006 11/01/2008 |
11/01/2006 11/01/2008 |
100 | 09/05/2006 11/13/2008 |
2 0 |
|
Begin Construction Phase
End Construction Phase |
05/01/2009 07/01/2011 |
05/01/2009 07/01/2011 |
05/01/2009 07/01/2011 |
100 | 10/07/2009 03/20/2014 |
-5 -33 |
|
Begin Closeout Phase
End Closeout Phase |
07/01/2011 12/01/2012 |
07/01/2011 12/01/2012 |
07/01/2011 12/01/2012 |
50 | 03/20/2014 12/29/2023 |
-33 -135 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 09/01/2010 | 09/01/2010 | 0 | 0 | |||
Implementation Date | 10/01/2010 | 10/01/2010 | 0 | 0 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 673 | 729 |
Peak Period Time Savings (minutes) | 45561 | 49354 |
Bond Funding Cost | |
---|---|
Adopted: |
$37,061,000 |
Current Approved: |
$18,568,000 |
Actual Expenditures: |
$18,568,000 |
Status as of December 31, 2023.